The Plan tab
Open a project and go to Plan. At the top you see your Launch target, how much buffer you have before launch (or how late you are), any Conflicts, and how many Vendors are involved.
- Vendor roadmap: one lane per supplier, showing what each one is doing and when. Click Add vendor to add one.
- Conflict badges flag problems: a task that starts before the one it depends on ends, work that runs through a factory closure, a supplier's stated lead time that's later than your plan, or a plan that lands after your launch date.
- Compare vendors: a lead-time chart across suppliers.
- Key decisions & notes: a running record of what you decided and why.
- Next steps: a checklist of what to do next.
Click Edit in timeline to change dates. If nothing is planned yet, click Open timeline.
The Timeline
The Timeline is a Gantt chart of your whole program.
- If it's empty, click Build my timeline to generate one from your project.
- Switch between Week and Month views.
- Click Add task to add work, and use Undo or Rebuild if you need to.
Factory holidays
- Choose a country under Holidays for. Its factory closures, such as Chinese New Year or Tet, are shown on the chart.
- Tasks are scheduled around closures. A bar that runs through one is marked Runs through a factory closure, and an alert tells you how many days closures add.
- Holiday dates are indicative. Confirm them with your factories.
Share the timeline with a supplier
- Assign tasks to a supplier first.
- Click Share with supplier.
- Send the bilingual message: Copy for WeChat, Send email, or Log in thread. You can also copy the Public link.
What the supplier sees:
- Only their own tasks and your project codename. Never prices.
- A read-only page where they can Confirm all dates or Propose new date.
What happens next:
- Proposed dates come back to you as Supplier change requests, which you Accept or Decline.
- You can see how many times the link was viewed.
- Links don't expire. They stop working when you Revoke them, or when you reject or delete that supplier.
Packages from the on-the-ground team line up their visit dates with the matching stages on this Timeline.
Cost & inventory simulator
The simulator is on the project Overview tab. Use it to try different quantities, freight and demand before you commit.
What you enter
- Unit price from: type a price, or use one from a quote or a supplier's key facts
- Order quantity and Unit price
- Tooling / NRE
- Shipping and Duty / tariff (%)
- Monthly demand
- Production lead time (days) and Safety stock (days)
What you get
- Landed / unit: the cost of one unit delivered
- Cash for this order: assumes a 30% deposit up front and the balance at shipping
- Reorder point: when to place the next order so you don't run out
- Stock-out risk
- A chart of your stock level over the coming months
- A breakdown of landed cost per unit
Click Reset to go back to the defaults. The numbers are estimates. For full detail per quote, use the landed cost calculator.